Home Design-Bid-Build I-95 Widening – Flagler County
Our Work

I-95 Widening – Flagler County

The project included widening I- 95 from four lanes to six, reconstructing a major interchange at SR 100 to a single-point urban configuration, milling and resurfacing the existing four lanes, widening two bridges over Lehigh Railroad Spur Canal, and replacing the bridge over the environmentally sensitive Pellicer Creek. The Superior Construction team reduced traffic impacts by designing and implementing a girder erection plan for the 243 LF steel plate girders at SR 100. This plan involved the preassembly of the girders into pairs on the ground and erecting the assembled units, effectively reducing by half the number of detours. To efficiently construct the project and accelerate certain components, the team divided the project into six 3-mile segments, allowing for half of the project to be accelerated in advance of the busy holiday season and reducing overall impacts to traffic.

Project Highlights
  • 18 miles of highway widening
  • 21 storm water retention ponds
  • 93,610 linear feet of storm drain piping
  • 243 linear feed of steel plate girders
  • 6, 3-mile segments
Client
Florida Department of Transportation (FDOT)
Location
Flagler County, FL
Completion Date

2009

Industry
Delivery Methods
Design-Bid-Build